In most cases, the order of these two phases is interchangeable and we will generally schedule whichever one is available first.
Think of the underground plumbing as the circulatory system of your pool. It circulates the water to and from the filter to keep your pool sparkling clean. And unlike our competition, at Royal Pools, we use two skimmers and 2 ½ inch pipe for greater circulation efficiency.
Inspections: Building Department Inspections may seem like an inconvenience at times, but they fulfill an important function. They’re there to make sure the contractor is building the project per the engineering specifications and the work is in compliance with all the relevant building codes.
Pre-Gunite Inspection: At this point, construction stops and we call for the pre-gunite inspection which is the first of several inspections by the building department. The timing for scheduling inspections can be charitably called challenging as we’re at the whim of a bureaucratic beast. One of the other things that separates Royal Pools from our competition is that we always have a person onsite to meet the inspector. They’re there to answer questions and provide information to facilitate the process which results in far fewer delays because of turndowns.
One other point regarding inspections; the pool plan and the building department inspection sign-off card are left at your property and will remain in place for the duration of the project. We place these in a PVC tube and usually hang it on the fence near the pool. Please make sure it is available when the inspector shows up.
Inspections: Once again, everything stops as we wait for the building department to inspect the electrical and gas work and this work must be signed off before we can proceed.
It is now time to for your concrete contractor to begin the forming and drainage work and preparation of the ground for the concrete deck. We will refer you to several experienced concrete contractors who specialize in decking around a swimming pool. That last part is really important, knowledge of the unique aspects of concrete around swimming pools is critical. The concrete work is usually a two week process.
If your project includes an auto-cover it will be installed after the pool is full of water. Each cover is custom made for your specific pool so it can take several weeks after the pool is full for the installation to take place.
Now that your pool is complete, you can take a breath and really start enjoying the experience of owning a Royal Pool. We know it will provide years of family enjoyment and trouble-free operation.